Blog
•
August 1, 2025
•
7 min read

Upgrading from Geiger-Muller Sensors to Flame Tracker Dry 325

Learn the steps to upgrade from Geiger-Muller flame sensors to Reuter-Stokes Flame Tracker Dry 325 (FTD 325) sensors.

Marcus Chen, PhD

Principal Application Engineer · Downhole
RS-N7 compensated neutron logging tool, prepared for downhole deployment in a Permian Basin operator's lab.

DISCLAIMER: Operators should completely read the Operation and Maintenance (O&M) manual before performing an upgrade. This document should be treated as supplementary to the O&M manual, not as a replacement.

The sensors, interconnect cables, and installation hardware mentioned in this document are all available from Reuter-Stokes. There are kits that aggregate the parts in appropriate quantities and are tailored to different gas turbines. Contact us for details!

CAUTION

Remove Geiger-Muller sensors from the sight tubes.

Inspect the sight tubes for restriction orifices.

Some sight tubes have small plates with holes inside the barrel of the sight tube that restrict the amount of light that reaches the flame sensors. If restriction orifices are present, they must be drilled out or the sight tubes must be replaced.

Remove all conduit from the space over the gas turbine

Often, the conduit will be connected to a junction box inside the turbine compartment. In that case, the junction box should be left in place as well as any conduit from the junction box to the control system.

If water cooling lines are present…

Remove them from the space over the gas turbine, then cap the lines at the main water supply pipes or other convenient point.

IMPORTANT: When handling the FTD 325 mineral insulated (MI) cables, do not bend the cable past the six inch minimum bend radius.

Avoid kinks because they will damage the sensor. Avoid sharp bends where the mineral insulated cables are connected to the hot ends and the cool ends.

Temporarily attach the hot end to the sight tube.

The hot end connects to the sight tube with a pipe union fitting. Connect the pipe union to the sight tube with hand tight torque only. Proper assembly will be done after functional testing.

Mount the MI cable to strut channel.

Use Reuter-Stokes installation hardware, including 1/8” cushioned loop clamps. 

The loop clamps include a silicone cushion that has a high temperature rating. See the O&M manual for details.

IMPORTANT: The cable must be secured at least every three feet.

At the cool end, the extra mineral insulated cable should be looped and mounted to a nearby strut channel using any convenient means.

Mount the cool end where the ambient temperature does not exceed 140°C.

In most cases, this is below the turbine on F-Class gas turbines or under the foot grating on E-Class gas turbines. Mount the cool end on a 1-5/8” strut channel using a 2-1/2” pipe clamp.

Attach interconnect cable to the MIL SPEC connector on the cool end.

Interconnect cables, RS part number RS-E2-0285PXXX, carry the 4-20 mA signal from the cool end to the control system. A right angle version of the cable is shown below. Dimensions are for reference only.

Turn the coupling nut on the connector until the blue line on the cable connector completely covers the red line on the housing connector – this indicates that the connector is fully engaged.

Route the conduit and the interconnect cable to the junction box.

The interconnect cable has a short, armored section on the connector end that provides electric shielding. The rest of the interconnect cable is not armored and must be routed through grounded conduit for electrical shielding. Ensure that only the armored cable section protrudes from the conduit. Route the conduit and the interconnect cable to the junction box. See the O&M manual for wiring details.

The strut channel used for mounting the cool ends must also be grounded.

Ensure that any existing cable meets or exceeds cable specifications.

In most cases, there will be a junction box in the turbine compartment and cable connecting the junction box to the control system. The cable should be 18 gauge, twisted, shielded pair. Ensure that any existing cable meets or exceeds this cable specification. Reuter-Stokes offers a spool of unterminated cable for this purpose, part number CB-37. The non-connector end of the interconnect cable will be attached to terminals in the junction box. See the O&M manual for wiring details.

Ensure that the power supply voltage is set correctly.

FTD 325 sensors are powered by 12-30 VDC, nominal 24 VDC. Geiger-Muller type sensors are powered by 300-350 VDC.

Ensure that the power supply voltage is set correctly before applying power to the FTD 325 sensors. Applying voltages >30 VDC can damage the FTD 325 sensors. See the FTD 325 O&M manual for details on power supply specifications.

If the control system is a GE Vernova Mark V…

It will only accept frequency signals for flame supervision. The output of the FTD 325 sensors is 4-20 mA. Reuter-Stokes offers a Flame Sensor Module (FSM), part number RS-FSM-1002-002, that converts 4-20 mA signals to frequency. The FSM is compatible with the Mark V. See the FSM manual for details. The FSM is a four-channel device and it must be installed in a safe area (non-hazardous) that is climate controlled, such as a PEECC. The FSMs are often installed adjacent to or inside the Mark V cabinets.

When using any GE Vernova control system…

Review all relevant GE Vernova bulletins and ensure that the threshold values in the control system are compliant.

Perform functional tests on all FTD 325 sensors.

Disconnect hot ends from sight tubes. At this point, they should be hand tight. Use an ultraviolet (UV) light source, such as the Reuter-Stokes UV penlight (part number FS-9000-LP), to perform a functional test on all the FTD 325 sensors. Read the outputs from the control system.
 

A purpose-built UV penlight is superior to open flames or flashlights for functional testing. Open flames have inherent safety risks. Flashlights can have different technologies, LED or incandescent, and have an unknown amount of UV light at unknown wavelengths. 

Assemble hot ends onto sight tubes.

Once the functionality of all sensors has been verified, assemble the hot ends onto the sight tubes. The flame sensor is installed to the sight tube using a pipe union. See the O&M manual for details on hot end assembly. It is key to ensure that the correct amount of torque is applied to properly attach the hot end.

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Vestibulum eget orci ullamcorper, euismod justo quis, ultrices mi. Donec accumsan sapien eu magna facilisis tempus. Nam varius sollicitudin justo non aliquet. Aenean aliquet lacus massa, eu consequat nunc gravida et. Proin ac elit vel ipsum posuere aliquam. Cras in tellus vitae leo molestie tristique.

What actually drives downhole detector response.

In hac habitasse platea dictumst. Nunc ultrices in erat sit amet dictum. Cras odio sapien, gravida a elementum id, placerat eget magna. Vestibulum consectetur metus eu elit pulvinar porttitor. Quisque vitae elit ligula. Sed eu rhoncus ipsum. Praesent tempus ultrices metus lacinia malesuada.

The detector parameters that actually matter for compensated logging response, in order of magnitude of impact:

The pressure-length tradeoff in practice.

Curabitur porttitor enim nunc, in imperdiet est venenatis id. Nunc molestie sapien sed leo aliquam, nec bibendum nibh dignissim. Cras eu felis vel mauris pretium volutpat. Nulla ultricies sapien at sapien venenatis lobortis. Mauris vel elementum tortor.

Sensitivity-vs-length curves for ³He at 1.0, 1.8, 2.5 and 4.0 atm — measured response from RS-P4 production data, normalized at L=300 mm.

Fusce vel viverra arcu, tempor sagittis leo. Sed ut massa tincidunt, sodales ipsum eu, rhoncus erat. Integer et nunc fermentum, commodo sapien tincidunt, rhoncus massa. Praesent scelerisque non lacus non condimentum. Nullam id dignissim augue.

“

Doubling the gas pressure delivers more sensitivity than doubling the active length — and ships in a smaller, more rugged package.

— Marcus Chen, RS Application Engineering

Sed vitae facilisis nisl. Cras sed dui aliquam, faucibus lacus eget, bibendum ex. Nullam congue justo eu ullamcorper vulputate. Curabitur vitae ligula aliquam, venenatis turpis quis, pellentesque diam. Proin faucibus ultrices vulputate.

Practical guidance for replacement spec.

When spec’ing a replacement detector for a fielded compensated neutron logging string, work the problem in this order:

Integer a volutpat massa, et pulvinar quam. Cras dolor nunc, hendrerit quis mattis eu, placerat a quam. Aenean auctor hendrerit pharetra. Pellentesque eu urna mauris. Donec eu justo sit amet eros porta ullamcorper quis eu est. Phasellus nec volutpat tellus.

More news & events

Blog

Proportional Counters for Radiation Measurement: Principles & Applications

Proportional counters are designed for the detection and measurement of ionizing radiation. They generate an electrical signal that is directly proportional to the energy deposited by the incident radiation, allowing for detection AND the characteri…
READ MORE →
Blog

Simple, Reliable Flame Monitoring – It’s Common Sense

The Reuter-Stokes approach to flame sensing originated in the core of nuclear reactors. Known for precision radiation measurements in harsh environments, the design practices that were learned in the reactor are used to sense flame presence in gas t…
READ MORE →
Blog

The Role of Flame Sensors in Gas Turbines

Infrared flame sensors are popular for industrial burner applications like boilers or furnaces. They are also sometimes used on gas turbines – but there is a drawback to this approach.
READ MORE →
Blog

Paragon x Reuter-Stokes: The New Era of Nuclear

The Paragon and Reuter-Stokes Gamma Metrics Neutron Flux Monitoring Systems (NFMS) strategic collaboration ensures continued reliability, effectively safeguarding a critical component of nuclear safety while addressing challenges such as technologic…
READ MORE →